Section 58 restrictions under the New Road and Street Works act 1991

Section 58

A section 58 restriction prevents statutory undertakers from digging up the road for a period of between one to five years after the road has been resurfaced or reconstructed, unless the work is an emergency or needed to provide a new customer connection.

Exempt Work

Works which are exempt:

  • Minor works that do not involve breaking up or excavating in the highway.
  • Immediate works for urgent or emergency purposes
  • Customer connections
  • Works to comply with either improvement notice or prohibition notice issued by the Health and Safety Executive under sections 21 or 22 of the Health and Safety at Work Act 1974.

If the proposed works does not fall within the exempt categories, they may still be able to go ahead. Approval from the authority will be required. Please email roadworks@sthelens.gov.uk giving information about the proposed works.

At present the following Section 38 restrictions apply:

ROAD NAMEWARDSTATUSRESTRICTION START DATERESTRICTION END DATEDESCRIPTION
MONTREY CRESCENTBillinge & Seneley GreenIn force23/12/202522/12/2028Footway Reconstruction
TITHEBARN ROADBillinge & Seneley GreenIn force13/08/202512/08/2027Carriageway Resurfacing
RAINFORD ROADBillinge & Seneley GreenIn force16/08/202515/08/2027Carriageway Resurfacing
MAIN STREETBillinge & Seneley GreenIn force18/08/202517/08/2027Carriageway Resurfacing
GARSWOOD ROADBillinge & Seneley GreenIn force13/08/202512/08/2027Carriageway Resurfacing
BIRCHLEY ROADBillinge & Seneley GreenIn force08/08/202507/08/2027Carriageway Resurfacing
BILLINGE ROADBillinge & Seneley GreenIn force21/08/202520/08/2027Carriageway Resurfacing
WAGON LANEBlackbrookIn force07/08/202506/08/2027Carriageway Resurfacing
LINFORD GROVEBlackbrookIn force12/08/202511/08/2028Carriageway Resurfacing
MARYLEBONE AVENUEBold & Lea GreenIn force09/02/202608/02/2029Carriageway Resurfacing
LEACH LANEBold & Lea GreenIn force24/04/202623/04/2029Carriageway Resurfacing
CLOCK FACE ROADBold & Lea GreenIn force24/04/202623/04/2029Carriageway Resurfacing
WALKERS LANEBold & Lea GreenIn force29/01/202628/01/2029Carriageway Resurfacing
ALFORD AVENUEBold & Lea GreenIn force20/01/202619/01/2029Carriageway Resurfacing
TARVIN CLOSEBold & Lea GreenIn force20/01/202619/01/2029Carriageway Resurfacing
BUDWORTH AVENUEBold & Lea GreenIn force20/01/202619/01/2029Carriageway Resurfacing
BURNAGE AVENUEBold & Lea GreenIn force14/01/202713/01/2030Carriageway Resurfacing
BODDEN STREETBold & Lea GreenIn force14/01/202713/01/2030Carriageway Resurfacing
POLLITT CRESCENTBold & Lea GreenIn force26/01/202625/01/2029Carriageway Resurfacing
BRINDLEY ROADBold & Lea GreenIn force27/07/202526/07/2027Carriageway Resurfacing
BRINDLEY ROADBold & Lea GreenIn force27/07/202526/07/2027Carriageway Resurfacing
CLOCK FACE ROADBold & Lea GreenIn force29/06/202528/06/2027Carriageway Resurfacing
MILL LANEBold & Lea GreenIn force04/07/202503/07/2027Carriageway Resurfacing
FOREST ROADBold & Lea GreenIn force21/09/202520/09/2027Carriageway Resurfacing
CHESTER LANEBold & Lea GreenIn force25/06/202524/06/2027Carriageway Resurfacing
KELSALL AVENUEBold & Lea GreenIn force25/06/202524/06/2027Carriageway Resurfacing
FARNDON AVENUEBold & Lea GreenIn force25/06/202524/06/2027Carriageway Resurfacing
SUTTON HEATH ROADBold & Lea Green/ Thatto HeathIn force01/09/202531/08/2028Junction Improvement
LOWFIELD LANEBold & Lea Green/ Thatto HeathIn force01/09/202531/08/2028Junction Improvement
ELTON HEAD ROADBold & Lea Green/ Thatto HeathIn force01/09/202531/08/2028Junction Improvement
SHERDLEY ROADBold & Lea Green/ Thatto HeathIn force01/09/202531/08/2028Junction Improvement
OSBORNE ROADEcclestonIn force06/03/202605/03/2029Carriageway Resurfacing
OAK TREE ROADEcclestonIn force27/02/202626/02/2029Carriageway Resurfacing
MILL BROWEcclestonIn force20/02/202619/02/2029Carriageway Resurfacing
KNOWLES HOUSE AVENUEEcclestonIn force17/02/202616/02/2029Carriageway Resurfacing
BROOKHOUSE GROVEEcclestonIn force09/02/202608/02/2029Carriageway Resurfacing
WALMESLEY ROADEcclestonIn force07/09/202506/09/2027Carriageway Resurfacing
PIKE HOUSE ROADEcclestonIn force13/08/202512/08/2027Carriageway Resurfacing
HOMESTEAD AVENUEHaydockIn force17/11/202516/11/2027Carriageway Resurfacing
TAYLOR ROADHaydockIn force17/11/202516/11/2027Carriageway Resurfacing
NORTH FLORIDA ROADHaydockIn force16/11/202515/11/2027Carriageway Resurfacing
RENFREW AVENUEMoss BankIn force21/11/202520/11/2027Carriageway Resurfacing
WOODLANDS ROADMoss Bank In force08/10/202507/10/2027Carriageway Resurfacing
PARKSIDE ROADNewton EastIn force31/05/202530/05/2028New Road Construction
PARKSIDE LINK ROAD EASTNewton EastIn force31/05/202530/05/2028New Road Construction
PARKSIDE LINK ROAD WESTNewton EastIn force31/05/202530/05/2028New Road Construction
WARGRAVE ROADNewton EastIn force30/07/202529/07/2027Carriageway Resurfacing
ASHTON ROADNewton EastIn force04/08/202503/08/2027Carriageway Resurfacing
VICTORIA ROADNewton EastIn force01/08/202531/07/2027Carriageway Resurfacing
MARKET STREETNewton WestIn force18/05/202617/05/2029Carriageway Resurfacing
WINSTON AVENUEParrIn force14/05/202613/05/2029Footway Reconstruction
NEVILLE AVENUEParrIn force10/04/202609/04/2029Footway Reconstruction
MCMINNIS AVENUEParrIn force17/10/202516/10/2027Carriageway Resurfacing
RUDD AVENUEParrIn force17/10/202516/10/2027Carriageway Resurfacing
HIGNETT AVENUEParrIn force17/10/202516/10/2027Carriageway Resurfacing
BROAD OAK ROADParrIn force11/10/202510/10/2027Carriageway Resurfacing
MANOR STREETPeasley Cross & FingerpostIn force02/03/202601/03/2029Carriageway Resurfacing
SUTTON ROADPeasley Cross & FingerpostIn force07/08/202506/08/2027Carriageway Resurfacing
PARK ROADPeasley Cross & Fingerpost/ St Helens Town CentreIn force17/03/202616/03/2029Carriageway Resurfacing
WOOD STREETPeasley Cross & Fingerpost/ St Helens Town CentreIn force30/07/202529/07/2027Carriageway Resurfacing
POCKET NOOK STREETPeasley Cross & Fingerpost/ St Helens Town CentreIn force10/08/202509/08/2027Carriageway Resurfacing
ST HELENS ROADRaiinfordIn force06/11/202505/11/2027Carriageway Resurfacing
DERBY DRIVERainfordIn force22/10/202521/10/2027Carriageway Resurfacing
HYDES BROWRainfordIn force28/08/202527/08/2027Carriageway Resurfacing
MOSSBOROUGH ROADRainfordIn force26/08/202525/08/2027Carriageway Resurfacing
ROSE PLACERainfordIn force24/10/202523/10/2027Carriageway Resurfacing
ROSE DRIVERainfordIn force24/10/202523/10/2027Carriageway Resurfacing
SANDWASH CLOSERainfordIn force31/10/202530/10/2027Carriageway Resurfacing
MOSSDALE DRIVERainhillIn force10/02/202609/02/2029Footway Reconstruction
WHARFEDALE DRIVERainhillIn force10/02/202609/02/2029Footway Reconstruction
WARRINGTON ROADRainhillIn force21/02/202620/02/2029Carriageway Resurfacing
MILLOM AVENUERainhillIn force12/02/202611/02/2029Carriageway Resurfacing
MALHAMDALE AVENUERainhillIn force23/02/202622/02/2029Carriageway Resurfacing
BISHOPDALE DRIVERainhillIn force23/02/202622/02/2029Carriageway Resurfacing
BLUNDELLS LANERainhillIn force03/02/202602/02/2029Carriageway Resurfacing
LAWTON ROADRainhillIn force14/08/202513/08/2027Carriageway Resurfacing
MOSSDALE DRIVERainhillIn force08/08/202507/08/2027Carriageway Resurfacing
WHARFEDALE DRIVERainhillIn force08/08/202507/08/2027Carriageway Resurfacing
WARBURTON HEYRainhillIn force04/08/202503/08/2027Carriageway Resurfacing
FIRST AVENUERainhillIn force25/07/202524/07/2027Carriageway Resurfacing
BATEY AVENUERainhillIn force25/07/202524/07/2027Carriageway Resurfacing
STANDISH STREETSt Helens Town CentreIn force20/03/202619/03/2029Carriageway Resurfacing
PETER STREETSt Helens Town CentreIn force25/07/202524/07/2027Carriageway Resurfacing
BURTONHEAD ROADSt Helens Town CentreIn force21/09/202520/09/2027Carriageway Resurfacing
BOROUGH ROADSt Helens Town CentreIn force09/03/202608/03/2029Carriageway Resurfacing
MEADOWCROFTSutton North WestIn force27/02/202626/02/2029Carriageway Resurfacing
CECIL STREETSutton South EastIn force05/03/202604/03/2029Carriageway Resurfacing
ORVILLE STREETSutton South EastIn force27/02/202626/02/2029Carriageway Resurfacing
MILL LANESutton South East/ Sutton North WestIn force14/12/202513/12/2027Carriageway Resurfacing
NUTGROVE ROADThatto HeathIn force20/02/202619/02/2029Carriageway Resurfacing
POYNTER STREETThatto HeathIn force10/07/202509/07/2027Carriageway Resurfacing
DOROTHY STREETThatto HeathIn force08/07/202507/07/2027Carriageway Resurfacing
SCHOLES LANEThatto HeathIn force13/07/202512/07/2027Carriageway Resurfacing
SCHOLES LANEThatto HeathIn force22/07/202521/07/2027Carriageway Resurfacing
DAWN CLOSEThatto HeathIn force10/07/202509/07/2027Carriageway Resurfacing
CLOSE STREETThatto HeathIn force10/07/202509/07/2027Carriageway Resurfacing
KNOWSLEY ROADWest ParkIn force23/03/202622/03/2029Carriageway Resurfacing
KNOWSLEY ROADWest ParkIn force28/09/202527/09/2027Carriageway Resurfacing
RIVINGTON ROADWest Park/ WindleIn force10/04/202609/04/2029Carriageway Resurfacing
COWLEY HILL LANEWindleIn force02/04/202601/04/2028Junction Improvement
GAMBLE AVENUEWindleIn force02/04/202601/04/2028Junction Improvement
BISHOP ROADWindleIn force02/04/202601/04/2028Junction Improvement
SWINBURNE ROADWindleIn force27/11/202526/11/2027Carriageway Resurfacing
SPINDLE HILLOCKBillinge & Seneley GreenProposed20/06/202619/06/2029Carriageway Resurfacing
CAMP ROADBillinge & Seneley GreenProposed19/06/202618/06/2029Carriageway Resurfacing
LOW BANK ROADBillinge & Seneley GreenProposed18/06/202617/06/2029Carriageway Resurfacing
BIRCHLEY ROADBillinge & Seneley GreenProposed01/01/202631/12/2028Footway Reconstruction
VICARAGE ROADBlackbrookProposed20/06/202619/06/2029Carriageway Resurfacing
WEST END ROADBlackbrookProposed20/06/202619/06/2029Carriageway Resurfacing
CLIPSLEY LANEBlackbrookProposed20/06/202619/06/2029Carriageway Resurfacing
FINGER HOUSE LANEBold & Lea GreenProposed18/07/202616/01/2027Surface Dressing
UNION BANK LANEBold & Lea GreenProposed18/07/202616/01/2027Surface Dressing
TIBBS CROSS LANEBold & Lea GreenProposed18/07/202616/01/2027Surface Dressing
GORSEY LANEBold & Lea GreenProposed18/07/202616/01/2027Surface Dressing
NEILLS ROADBold & Lea GreenProposed18/07/202616/01/2027Surface Dressing
TENNYSON STREETBold & Lea GreenProposed20/06/202619/06/2029Carriageway Resurfacing
WALMESLEY ROADEcclestonProposed20/06/202619/06/2029Carriageway Resurfacing
ECCLESFIELD ROADEcclestonProposed20/06/202619/06/2029Carriageway Resurfacing
ROSE AVENUEHaydockProposed20/06/202619/06/2029Carriageway Resurfacing
NORMAN AVENUEHaydockProposed31/03/202630/03/2028Carriageway Resurfacing
SOUTHWARD ROADHaydockProposed31/03/202630/03/2028Carriageway Resurfacing
CITY ROADMoss BankProposed20/06/202619/06/2029Carriageway Resurfacing
WASHWAY LANEMoss BankProposed20/06/202619/06/2029Carriageway Resurfacing
HIGH STREETNewton EastProposed20/06/202619/06/2029Carriageway Resurfacing
HIGH STREETNewton EastProposed20/06/202619/06/2029Carriageway Resurfacing
STANLEY STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
HAYDOCK STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
OXFORD STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
CHEMICAL STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
EARLE STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
QUEEN STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
BRIDGE STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
MARKET STREETNewton WestProposed31/03/202630/03/2029Public Realm Development
HIGHER PARR STREETPeasley Cross & FingerpostProposed20/06/202619/06/2029Carriageway Resurfacing
ASHCROFT STREETPeasley Cross & FingerpostProposed20/06/202619/06/2029Carriageway Resurfacing
PARR STOCKS ROADPeasley Cross & FingerpostProposed20/06/202619/06/2029Carriageway Resurfacing
OLD LANERainfordProposed20/06/202619/06/2029Carriageway Resurfacing
WARRINGTON ROADRainhillProposed20/06/202619/06/2029Carriageway Resurfacing
CORPORATION STREETSt Helens Town CentreProposed11/07/202610/07/2029Footway, Carriageway
CLAUGHTON STREETSt Helens Town CentreProposed20/06/202619/06/2029Carriageway Resurfacing
MILL LANESutton South East/ Sutton North WestProposed20/06/202619/06/2029Carriageway Resurfacing
ADELAIDE AVENUEThatto HeathProposed20/06/202619/06/2029Carriageway Resurfacing
CANBERRA AVENUEThatto HeathProposed20/06/202619/06/2029Carriageway Resurfacing
OLIVER ROADWest ParkProposed20/06/202619/06/2029Carriageway Resurfacing
CANTERBURY STREETWindleProposed20/06/202619/06/2029Carriageway Resurfacing

 

 

 

Last modified on 19 May 2026